Turn of multiple parent tasks
Sometimes a task is assigned to two parent tasks. And it is difficult to seperate them. However we never use this. So maybe there could be a option where this can be turned off completely?
Il semble que nous n'ayons pas la page traduite que vous cherchez, mais nous avons d'autres contenus en anglais et offrons une assistance en anglais.
Que pouvons-nous faire pour vous ?
Apprendre. Partager. Discuter.
Sometimes a task is assigned to two parent tasks. And it is difficult to seperate them. However we never use this. So maybe there could be a option where this can be turned off completely?
Folllowing List for Post: Turn of multiple parent tasks
[this list is visible for admins and agents only]
I concur. Further, this along with the way the system limits alignment of dates based on dependency mapping to parent tasks is not at all user friendly. I should be able to create a parent task with a group of subtasks where the parent task takes on the earliest start and latest due date of the group of subtasks. I should then be able to use the parent task as a dependency for another task for auto scheduling.
Seamless auto scheduling is core function that is really missing from this solution.
Welcome to the Community, Melisa Shearin, and thank you for supporting Angelique's suggestion here!
Lisa Community Team at Wrike Wrike Product Manager Devenez un expert de Wrike avec Wrike Discover
Lisa Wrike Team member Devenez un expert de Wrike avec Wrike Discover