Define when recurring tasks should be created

Hi, I understand that recurring tasks get created one working day in advance, but I would like if I could specify when the next recurrence is created, or the option to say that the next reccurence should be created when I complete the current reccurence.

The reason for this is when I on Sunday plan my week the recurrings tasks that will be due on Tuesday and onwards are not yet created = my planning soon crashes :)

I hope this was understandable.

Upvote 10
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
4 commentaires

I'm shocked this doesn't have more votes!

Based on the documentation, I assumed it would create the next task as soon as the previous one was completed. It reads, "you specify how many tasks you want to have in the workspace at a time until the recurrence ends." I have specified that I want 1 task at a time to exist, which would seem to mean that there will always be 1 task in the workspace. But if I have it set to 1, there are usually 0 tasks in the workspace. 

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Yeah, with three votes I guess this will never be fixed :(

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

The workaround seems to be setting the number of tasks to 2. That way, there's always at least 1. Makes perfect sense. :)

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hmm, I thought I've tried that, but will have another look :)

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Define when recurring tasks should be created