Gantt Chart and Predecessors

Good morning. When I have a project, as an example, that has 50 tasks, Let's say task (line item) number is 5.  Task #12 shows #5 is its predecessors, FS. When I delete or add another task, my predecessor is now a different line item # and I have to review all tasks again that have predecessors and update with the new line item #. Am I doing something wrong?

 

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
1 commentaire
Avatar
Aaron K.

Hi Marilyn Ehlebracht,

Thank you for your question!

When a task's line position changes on the Gantt chart, for example when you change the sorting of the chart, the predecessor column automatically updates to reflect the change. Take a look at this series of screenshots to see what I mean. Changing the sorting will change the line position of the tasks, but the dependencies stay the same and the predecessor column adjusts automatically:

​​Please give it a try and let us know what you think 😊

Aaron K. Community Team at Wrike Wrike Product Manager En savoir plus sur les fonctionalités et les meilleures pratiques grace à nos Webinaires online

Aaron K. Wrike Team member En savoir plus sur les fonctionalités et les meilleures pratiques grace à nos Webinaires online

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Gantt Chart and Predecessors
[this list is visible for admins and agents only]

Haut de la page
Didn’t find what you were looking for? Write new post