Adding new tasks on Gantt view

Hi Wrike Community! 

I used to add tasks directly on Gantt View using a keyboard shortcut. I have not been able to do so in the past few weeks. Have the shortcuts changed recently? I've tried all variations of the shortcut but cannot get it to work. I use the Wrike for Mac desktop app. I'd appreciate any help you can give me with this. Thanks!

 

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
2 commentaires
Avatar
Aaron K.

Hi Cristina Villarreal,

Thank you for your question!

The keyboard shortcut for adding a new task to the Gantt chart (Alt+Shift+Click) only works when you have your Gantt view sorted "By Gantt manual order":

All other keyboard shortcuts for the Gantt chart can be found here and should work in all of the sorting options.​

Please give it a try and let us know if you have questions. 😊

Have a productive day!

Aaron K. Community Team at Wrike Wrike Product Manager En savoir plus sur les fonctionalités et les meilleures pratiques grace à nos Webinaires online

Aaron K. Wrike Team member En savoir plus sur les fonctionalités et les meilleures pratiques grace à nos Webinaires online

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Thank you so much @... 😄

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Adding new tasks on Gantt view