Issues with creating and rescheduling a project from a Blueprint that contains milestone tasks
Hello,
I have set up Blueprints that contain tasks, dependencies and resources. We then create project plans from the Blueprints, check the "Reschedule" box and set the new start date.
If the Blueprint contains no milestone tasks, then the project reschedules correctly to the new start date
If the Blueprint contains milestone tasks, it does not reschedule correctly and gives unexpected and wrong results
Because of this issue, I am currently setting up Blueprints without milestone tasks, but would like to do so going forward. What should be the correct behavior of a Blueprint that contains milestone tasks? Should they reschedule properly?
Hi Andy Sigrist, I believe our Support team is helping with this.
If you need anything else, don't hesitate to ask 👍
Elaine Community Team at Wrike Wrike Product Manager En savoir plus sur les fonctionalités et les meilleures pratiques grace à nos Webinaires online
Elaine Wrike Team member En savoir plus sur les fonctionalités et les meilleures pratiques grace à nos Webinaires online
Hello I also had a similar issue last week (and didn't previously used to have it). For me all the tasks rescheduled correctly, except those attached to a milestone where the milestone didn't move. Can anyone let me know if there is a solution for this? or if this is a known issue?
Hello David Benjamin, I see that our Support team is in contact with you via email.
Please let me know if I can help with anything else 🙋🏻♀️
I am experiencing similar issues. Has an easy fix been identified for this?
Hi Isabelle Couture, I'm sorry to hear you're experiencing this! I've asked my colleagues from the Support team to contact you about this to troubleshoot. I can see they've already reached out to you via email 👍
Please let me know if I can help you with anything else!
Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover
Lisa Wrike Team member Become a Wrike expert with Wrike Discover
I have the same issue with the milestones. Any guidance?
Hi Lea Labastida, thank you for bringing this to us! I have opened a ticket with our Support team so they can assist you with this 👍
The same issue has emerged for us. Can you please get in touch?
Hey Teddy, absolutely, I've raised the ticket now 🙌
Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover
Lisa Wrike Team member Become a Wrike expert with Wrike Discover
Hello! I have the same problem. Any guidance?
Hi Lisa can you share a solution in this post?
Hi Idoya Sanz, I've raised a ticket for you with our Support team so they can investigate further, they'll be in touch shortly.
Pietro Poli, we're not entirely sure on the cause yet Pietro, so I don't want to share information here that may not be accurate for everyone. Would you like me to raise a ticket for you also?
Elaine Community Team at Wrike Wrike Product Manager En savoir plus sur les fonctionalités et les meilleures pratiques grace à nos Webinaires online
Elaine Wrike Team member En savoir plus sur les fonctionalités et les meilleures pratiques grace à nos Webinaires online