Timelog Entries per task assigne
I'm trying to create an analytics to allow Project Managers see how much time is being recorded against tasks by assignees across their portfolio of projects. However, it would appear that the only option for Time recorded is actually based on the time recorded against the task and not that of the individuals.
Is there anyway of using some of the limited formulae in Wrike analyze to obtain this information? Below is an image of what I mean. I've removed names and replaced with Person X.
5th Column is Task assignee, 7th is time logged, 8th is time log username. As you can see the time actually logged was a total of 1hr 45min however none of it was by the task assignees.
Hi Scott McKinley,
try to invert 7th and 8th columns.
It must work.
That's not what I'm looking for though. I don't want to use the Timelog user at all, I want to see time logged by the resources assigned to the task.
Scott you cannot achieve this because timelog are tied to Timelog User and not to Assignee.
You need to change 5th column to Timelog User =)