Sub Tasks Rollup to Task

Hi,

Need a little help please.ย  ย ๐Ÿ™‚ย  For some reason when I have subtasks and change the date for one of them it does not update the date for the main task.ย  Is there a way to correct this?ย  I'm usually in Gannt or Table view.

Thank you for your help,

Joe

0
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos
1ย commentaire

Welcome to the Community Joe Kniffen ๐Ÿ‘‹

Per this Knowledge Base article, there are some exceptions to the alignment rule - if they are milestones or a part of dependencies. Can you please let me know if your case is covered by these exceptions?ย 

ย 

Lisa Community Team at Wrike Wrike Product Manager Devenez un expert de Wrike avec Wrike Discover

Lisa Wrike Team member Devenez un expert de Wrike avec Wrike Discover

0
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

Folllowing List for Post: Sub Tasks Rollup to Task