Dependencies moving other tasks
Can you have a dependency and have it not change the connected tasks dates when you adjust or move one of the tasks?
help.wrike.com/hc/en-us/articles/209604229-Dependencies-on-the-Gantt-Chart-
Кажется, у нас нет переведенной страницы, которую вы ищете, но у нас есть другой контент на английском языке и поддержка на английском языке.
Чем мы можем вам помочь?
Учиться. Делиться. Обсуждать.
Can you have a dependency and have it not change the connected tasks dates when you adjust or move one of the tasks?
help.wrike.com/hc/en-us/articles/209604229-Dependencies-on-the-Gantt-Chart-
Folllowing List for Post: Dependencies moving other tasks
[this list is visible for admins and agents only]
Hi Haley, happy to see you on Wrike Community 🙂
When you reschedule a task with dependencies, all dependent tasks are automatically rescheduled, this is by design. At the same time, you can shift the dependency chain to preserve the gaps between tasks when you reschedule tasks in this way. Please let me know if that can help you 🙏
Lisa Community Team at Wrike Wrike Product Manager Станьте экспертом Wrike с Wrike Discover