[Status: Launched 🚀] Feature to easily show schedule Plan vs Actual

Wrike should provide an easy way to see schedule plan vs actual.  If there is already a way, please advise.

Upvote 5
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
Комментариев: 4
Официальный комментарий
Avatar
Stephen

Hi guys, Baseline is now available in Gantt view. Check it out! I'll be changing this request to launched but feel free to provide further feedback on the thread I've linked to.

Thanks for your votes and feedback around this feature 🙌

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Agreed.  A baselining feature at the very least to capture plans as they change.

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
Avatar
Stephanie Westbrook

Hi Karen! I moved your post to the Product Feedback section so we could more easily share your suggestion with the Product Team. Could you take a look at Ben's post and let me know if you were looking for something like that?

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

It would be very useful to be able to compare a baseline for the project to the actual/current dates scheduled when in the Gantt Chart view.  This was functionality that I frequently used in MS Project. 

Perhaps there could be a way (an action/button) to "capture" the current schedule for the entire project (tasks and subtasks) and have that be saved as the project's baseline for comparison in the future.

4
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos