How to show Milestone tasks in Wrike Analyze

We're trialling using Wrike Analyze to create High Level Reports for our projects, and one of the items we'd like to show is the state of Milestones.  Now in Wrike you can convert a task to be a milestone, however, I can't seem to see anyway of just showing these milestones.

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
1 комментарий

You can use the 'Task Planning Type' data attribute in analyze to filter down to milestones!

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos