Problem with dependencies
Hello Wrike Community! :)
I'm having a bit of an issue with dependencies and predecessors. No matter what I do, for some reason changing the predecessor, dependency type and even adding lag/lead time doesn't change the task dates.
I have never seen this happen before. Any ideas?
Thanks!
I have been experiencing this as well.
Robin Hayes I'm wondering if it is related to this:
https://help.wrike.com/hc/en-us/articles/360009420853-Roll-Up-Dates-on-the-Gantt-Chart-
Renato Angelo Oh yes, very possible. Just did a test project to play with that a little bit. I think that might be it. Will put it to the test in some current projects. Thanks! 😀
Hi Renato Angelo, welcome to the Community! Hi Robin Hayes!
As Renato shared, if you enable the date roll up feature the task dates will be automatically rescheduled 👀
Cansu Community Team at Wrike Wrike Product Manager Aprenda sobre as funcionalidades e melhores práticas em Wrike com o nosso Treinamento Webinar Online
Cansu Wrike Team member Aprenda sobre as funcionalidades e melhores práticas em Wrike com o nosso Treinamento Webinar Online
Cansu thanks for the welcome and for jumping in here.
Still, with the roll up feature enabled, dependencies are not working. Do you have more information about this problem?
Hi Renato Angelo, I see that my colleagues from the Support team are in touch with you via email about your question. Please let me know if I can help you with anything else 🙋🏻♀️
Cansu Community Team at Wrike Wrike Product Manager Aprenda sobre as funcionalidades e melhores práticas em Wrike com o nosso Treinamento Webinar Online
Cansu Wrike Team member Aprenda sobre as funcionalidades e melhores práticas em Wrike com o nosso Treinamento Webinar Online