Project progress on Gantt view

Hello,

I'm very new to Wrike, so please forgive if this is an obvious question with an obvious solution.

In the Gantt Chart View of a project, the top bar that encapsulates the project can be filled in. What does this mean and how is it changed? Is this the "progress" of the project? If so, how do you control/record this?

Thanks,

Marek

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
3 comentários
Hey Marek, welcome to Wrike Community 🙂
Can you please check whether you've enabled an experimental feature "Roll Up Dates in Gantt Chart" from Wrike Labs? If you have, then the bracket representing a Project on the Timeline shows whether or not a Project has Tasks which fall outside its dates. The part that spans the Project's own dates has the filling, and the part representing dates of Tasks which fall outside has no filling: 
 So I guess if you've enabled the feature and the entire bar has no filling as on your screenshot, it means that all the Tasks in the Project fall outside its dates.
Please let me know if that helped you 🙌
 

Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Lisa Wrike Team member Become a Wrike expert with Wrike Discover

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hi Lisa, Thanks for the info. I did have the Roll up Dates in Gantt Chart enabled. That explains this functionality.

Is there a way to determine % complete of a project from the Gantt Chart view?

Cheers.

 

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

@Marek Hey, very exciting news - Project Progress is now launched 🎉 Please find more info in Brought to you by Wrike and on our Help Center

Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Lisa Wrike Team member Become a Wrike expert with Wrike Discover

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos