Automation: Assign Successor Task Once Predecessor Task Is Completed

I'm looking to see if there is automation option for when a predecessor task is marked completed, that it will then assign out the successor task and mark it as active. Where before the successor task was not assigned to anyone and would have been in a cancelled status, but we are calling this status "Queued".  

Is this a current automation process?

3
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Automation: Assign Successor Task Once Predecessor Task Is Completed
[this list is visible for admins and agents only]

Topo

Próximas sessões ao vivo