Convert Milestone to Task - mass edit

Does anyone know an easy way to convert 500+ milestones to regular task?  We can do a mass edit to milestone but can't go back... any work arounds or just a manual edit? 

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
3 comentários

Hi Norma Hansen, thank you for reaching out! 

It is possible to mass edit milestones with Advanced rescheduling options - you can clear the dates for them or setting the start and due dates:

Can this help? 

Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Lisa Wrike Team member Become a Wrike expert with Wrike Discover

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

How do I do the opposite... mass edit to convert tasks to milestones?

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
Avatar
Juan

Hi Teresa Skaar, welcome to the Community! Thank you for sharing your question with us. A milestone is basically a task with only a due date set - and no start date. For this reason, if you remove the start dates from your tasks, you will convert them into milestones.

You can easily achieve this by either clearing the start dates of one of your tasks in the New Table View and then drag-and-drop this (empty) value.
 
  
 
Once you clear the start dates, the tasks will be converted into milestones.
 
I'd also like to mention that you can visit our New to Community forum to check the available resources you can find in the Community 🙂 If you have any additional questions, please let us know.
0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Convert Milestone to Task - mass edit
[this list is visible for admins and agents only]

Alto
Didn’t find what you were looking for? Write new post