[Status: Launched! ๐Ÿš€(in Wrike Labs)] Prevent Automatic Rescheduling of Tasks When Using the Work Scheduling Feature

We currently do not use the work scheduling feature. We love the new Wrike Resourcing tool and are implementing it now. In order for that tool to be as accurate as possible we need to start using the work scheduling feature.

Our company has two days off next week for Thanksgiving. All due dates currently set in Wrike already took that into account. If I add the two days as a company holiday over 1,000 tasks in Wrike will have their due dates pushed out by 2 days and they will all have to be manually reset.

We often have employees request last minute PTO. We usually grant these requests with the caveat that since we are granting a last minute request for PTO they must still meet their current due dates and they will not be moved. If we put that PTO in work scheduling their due dates will be moved anyway.

The automatic feature is nice, and I can see many instances where it will be helpful, but users should NEVER be forced into automatic task rescheduling, it should be an option. This is also an issue with task dependencies. We currently do not use this feature because of the nature of our projects often require us to move a single task due date without wanting to change subsequent task due dates. We would really like to use dependencies but it is too much of a hassle because of this.

Automatic features are good but should never be mandatory. This should be considered in all current and future design as a best practice.

Votar a favor 66
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos
36 comentรกrios

Karina Sansomย I'm glad to hear I was able to help ๐Ÿค—

Lisa Community Team at Wrike Wrike Product Manager Torne-se um especialista em Wrike com o Wrike Discover

Lisa Wrike Team member Torne-se um especialista em Wrike com o Wrike Discover

1
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

@..., good to know; thanks!

0
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

Following up on this - I enabled the labs feature, and I have noticed now I dont see any notification when I assign something or try to @ someone who is marked on vacation that day.

I didnt notice until a team member pointed it out, and a deliverable was delayed and I had to reassign last minute.

ย 

I think the notifications are still important - it was just the reassignment that was a problem.ย 

0
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos
Avatar
Cansu

Hi Austin Headley, thank you for posting! I've shared your feedback with the team ๐Ÿ‘๐Ÿผ

0
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

I no longer see this in Wrike Labs. Is it part of the core product now?

0
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos
Avatar
Juan

Hi Crystal Fugate, as stated in our Help Center, if you're an account admin, you should be able to see the option to Disable automatic task reschedulingย in Wrike Labs.ย 

May I please ask you to elaborate a bit on your case so we can provide you with an accurate reply?

Thank you!

0
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

Folllowing List for Post: [Status: Launched! ๐Ÿš€(in Wrike Labs)] Prevent Automatic Rescheduling of Tasks When Using the Work Scheduling Feature
[this list is visible for admins and agents only]

Topo

Prรณximas sessรตes ao vivo

Nรฃo encontrou o que estava procurando? Escreva um novo post