Dependency tracking & baseline reporting
Hello,
Im looking to be able to track the movement in my project plan and to allow me to report to stakeholders the impact an exception has on a project.
Working example is i'm currently moving a task on the critical path and i need to inform stakeholders on the impact. But i initially only want to present this as an option so would like to undo the change after. ideally id like to be able to produce either a 'before and after milestone view'. or somehow show the impact on the timeline view.
Thanks
Hi Michael - I had a call with Wrike this week and they mentioned that functions like these are coming in future releases - but no dates provided. I am looking forward to this year's Wrike conference to get a read on this. It would really be helpful! - Candice
I am using a workaround to link tasks to other tasks and using dependencies, since they are the only way to link tasks to each other in wrike. This would be great in order to help me report on this!