Set weekly resource capacity lower
We like to set our weekly resource capacity between 30-35hrs/week depending on the resource. It allows employees to not get overloaded with five 8 hour work days. Giving the hour or so of breathing room each day helps reduce work overload.
Hi Steven Scales, thank you for creating this post. You can create a custom daily capacity and then apply it to the relevant users. Here is how you can achieve this.
Please, let us know if this is what you were looking for and if you have any additional questions 🙂