self calculating start date of Tasks
When I have two main tasks. Let's say task 1 and task 4. Task 1 has two sub-tasks, task 2 and task 3.
Task 4 starts when task 1 ends. The duration of task 1 corresponds to task 2 and / or task 3. In this case, if task 2 or 3 is changed, the start date of task 4 should be calculated according, so that it begins when task 2 and / or 3 have expired.

The top-level task end date should automatically adjust based on the end date of the subtasks, which would solve for the dependency issue noted here. According to this thread it's "coming soon": https://help.wrike.com/hc/en-us/community/posts/115000153945--Status-Coming-Soon-Allow-Subtasks-to-Update-Start-and-End-Dates-of-Parent-Tasks
I agree, and currently have to setup dependencies from each of the subtasks as a work around (i.e. create a dependency from task 1 to task 4, task 2 to task 4, and also task 3 to task 4 in your example).
Thank you for the feedback here Stefan Kellenberger, Meredith Selden! We'll be updating the above mentioned thread again as soon as we hear from the Product team 👍
Lisa Community Team at Wrike Wrike Product Manager Torne-se um especialista em Wrike com o Wrike Discover
Lisa Wrike Team member Torne-se um especialista em Wrike com o Wrike Discover
Anxiously waiting for this item. I found out the hard way that it was not working.
Rohan V Community Team at Wrike Wrike Product Manager Torne-se um especialista em Wrike com o Wrike Discover
Rohan V Wrike Team member Torne-se um especialista em Wrike com o Wrike Discover