Enhancement for Task highlight
We have added custom field called as Estimated Time for task as shown below,
- Can I get some task highlight when actual time is more than Estimated time. I am also ok if we can see this highlight in Report.
- Secondly I have added below check box list to task, can I add dependency where until below all check box are not checked system will not allow to mark task complete?

Hi Samir welcome to the forums! For your second point, we can definitely pass the feedback to our product team. In terms of current functionality, you can create dependencies between tasks. It sounds like that won't work for your use case though?
Hi Stephanie,
Thanks for your positive feedback. Dependencies between task will not work for my use case. happy to know that you are sharing this isdea to Development team.
Regards,
Samir
Got it, just wanted to make sure! Thanks 🙂