Votar a favor
16
Folllowing List for Post: Option for hiding sub-tasks in shared timeline
[this list is visible for admins and agents only]
Parece que não temos a página traduzida que você está procurando, mas temos outros conteúdos em inglês e oferecemos suporte em inglês.
Como podemos ajudar você?
Aprender. Compartilhar. Discutir.
Folllowing List for Post: Option for hiding sub-tasks in shared timeline
[this list is visible for admins and agents only]
There should be a option for hiding sub-tasks in a shared timeline view. For example we have internal sub-tasks that we dont want our customers to see, however we do want to share the parent task timeline view with them
Hi Huzefa, thanks for sharing this idea! I wanted to share a post I wrote earlier, which includes some tips on customizing the Timeline VSnapshot so it displays only the info you want a client to see: Share and Customize Timeline Data. Happy to answer any questions about that!