William Weinberger commented,
  1. Community
  2. Product Feedback
  3. Rename Default Custom Fields

I already created the "Actual" fields.  The issue is that the Start Date, Due Date, and Duration are used in the Gantt Chart and I would like to name them to reflect my understanding if what they r...

Avatar
William Weinberger commented,
  1. Community
  2. Product Feedback
  3. Rename Default Custom Fields

The reason I asked about the renaming of system fields is because of the following set of dates - Start Date, Due Date, and Duration.  I have asked the following question to a few of you support te...

Avatar
William Weinberger commented,
  1. Community
  2. Product Feedback
  3. Rename Default Custom Fields

My previous comment referenced system fields.  I  meant to ask the question with respect to custom fields, which is the subject of the discussion. However, I may as well ask.  Can system fields be ...

Avatar
William Weinberger commented,
  1. Community
  2. Product Feedback
  3. Rename Default Custom Fields

So, I never saw a conclusion to this question/subject. Can System Field names be changed? ... and when a rename takes place (whether custom or system), do all references to that field get updated a...

Avatar
William Weinberger commented,
  1. Community
  2. Product Feedback
  3. [Status: Coming Soon...🕑] Allow Subtasks to Update Start and End Dates of Parent Tasks

I did read thru some of the notes and want to confirm my understanding.  The sequence of steps is to: 1. Rollup the start date (which is the minimum function) 2. Rollup the duration (which is the m...

Avatar
William Weinberger commented,
  1. Community
  2. API and Developers
  3. Conditional Statements, Loops, Logical Operators

Add my vote for this functionality.  Allowing conditional statement in formulas would be very useful/helpful.

Avatar
William Weinberger commented,
  1. Community
  2. Product Feedback
  3. Advanced Conditional Logic in Request Forms and Table View (math. formulas) along with populating the data to another report or table

I am not sure of this is the intent of this suggestion or not.  If not, consider this a new suggestion.  Or, if this functionality exists, please point me to the appropriate article/documentation. ...

Avatar
William Weinberger commented,
  1. Community
  2. Product Feedback
  3. [Status: Coming Soon...🕑] Allow Subtasks to Update Start and End Dates of Parent Tasks

+1 for me.  I find it hard to believe the amount of time this request/issue has been open.  I just tried this and only the highest level task get rolled up, not any of the subtasks. I would like to...

Avatar
William Weinberger commented,
  1. Community
  2. Product Feedback
  3. More intuitive way to change task start and due date

I comment was due to a filter I forgot existed.  I forgot what filter I had in place but when I attempted to update either the start or due date, the task would disappear (it would be filtered).  I...

Avatar
William Weinberger commented,
  1. Community
  2. Product Feedback
  3. More intuitive way to change task start and due date

It is clearly not intuitive how to update a task's start date, due date, and duration.  I found when attempting to update either of the tasks, the task disappears.