Activity overview

I use the List view for planning a project and the Timeline view for monitoring execution of the project. The List view has options for creating and assigning tasks that are not available on the Ti...

How can I make the LIST view sort match the TIMELINE sort if a task is dragged on the TIMELINE view? If a task is reordered in the TIMELINE view, this does NOT change the task's Priority. So, the o...

What is the new default sort order of tasks in the Timeline view? If I manually reorder a task in the table, does this change the Priority or some other field? Unfortunately, I don't see how this ...

Sorting tasks based on start date and duration does not sense for projects like ours where most tasks have Finish-to-Finish dependencies. On the List view we sort tasks by Priority. That should be ...

Sorting tasks based on start date and duration does not sense for projects like ours where most tasks have Finish-to-Finish dependencies. On the List view we sort tasks by Priority. That should be ...