Matt Stroot ha commentato,
  1. Community
  2. Product Feedback
  3. [From Wrike] Your Feedback: Leads and Lags for Dependencies in Gantt Chart

Thank you Brianna, I was actually in the Table View (misunderstood the direction).  Got it now, thanks!

Avatar
Matt Stroot ha commentato,
  1. Community
  2. Product Feedback
  3. [From Wrike] Your Feedback: Leads and Lags for Dependencies in Gantt Chart

When following the instructions in the Knowledge Base Article, I do not see an option for 'predecessors' when creating a column.  The only options I see are:  ID, Assigned to, Time Spent, Start, Du...

Avatar
Matt Stroot ha commentato,
  1. Community
  2. Product Feedback
  3. [Status: Launched 🚀] Leads and Lags with Dependencies

Another vote to have this created!  For us, we would like to be able to set a start date and then have another task dependent on that start date, but the next task doesn't actually started for 30 d...

Avatar
Matt Stroot ha creato un post,
  1. Community
  2. How To

When setting up dependencies, is there a way to add a time buffer?  For example, I want task B to be dependent on Task A, but I do not need to start task B until a week after Task A is completed?  ...