Just want to share with the community that I finally got this working within Integrate. I wish I was able to do something similar with the hours assigned in the workload but here aren't events for ...

Sure Juan! I got the response yesterday afternoon so here it is. BTW, not the best answer a Pinnacle and Integrate client will want, but here we go: Indeed, it is possible to notify the Project ...

Hey Pietro Poli still waiting for a response!

Just to complement, there is trigger that can be fired when a task is updated but there is no way to know which field was updated. In particular, im interested to know when the task gets reschduled.

Is there a way to know when a task is rescheduled? I will like to notify the project owner when that happens. I dont see how to do it in Integrate nor in the API. Can you please help?

Hola wrike! Thanks for this information.

This is something we will value too.
Kudos