  1. Сообщество
  2. Product Feedback
  3. [Status: Re-launched! 🚀] Bring back Date Constraints

Awesome!  Many thanks to the wrike team! --- Dave

  1. Сообщество
  2. Product Feedback
  3. [From Wrike] Your Feedback: Leads and Lags for Dependencies in Gantt Chart

The new lag/lead feature seems to work well, and the effort on that is appreciated.  However others may not be aware that the Date Constraint functionality was removed with this update.  For our te...

  1. Сообщество
  2. Product Feedback
  3. [Status: Re-launched! 🚀] Bring back Date Constraints

It seems like there was an expectation that lags could replace date constraints.  But those are not the same thing.   Lag:   Constraint: --- Dave

  1. Сообщество
  2. Product Feedback
  3. [Status: Coming Soon...🕑] Allow Subtasks to Update Start and End Dates of Parent Tasks

So I was checking out the latest wrike labs today, and what do I see? After I checked my calendar to make sure it wasn't April 1, I tried it out.  The new right-click option called Item Rollup adj...

  1. Сообщество
  2. Product Feedback
  3. [Status: Backburner ⌛️] Customize Conflict Monitor

A workaround that may help... While the built in Dashboard Widget shows conflicts for the entire account, the Analytics View shows conflicts only for the selected folder. As noted, clicking on a c...

  1. Сообщество
  2. Product Feedback
  3. [Status: Coming Soon...🕑] Allow Subtasks to Update Start and End Dates of Parent Tasks

Our csm Dury was kind enough to let me meet with the developer of the subtask alignment feature.  I showed him the 'Auto Scheduled' mode for parent tasks in MS Project, which seems to be everyone's...

  1. Сообщество
  2. Product Feedback
  3. [Status: Coming Soon...🕑] Allow Subtasks to Update Start and End Dates of Parent Tasks

one last post to illustrate...

  1. Сообщество
  2. Product Feedback
  3. [Status: Coming Soon...🕑] Allow Subtasks to Update Start and End Dates of Parent Tasks

Agree with Brad.  I was hoping this would be a task scheduling option (ie "Rollup") that would silently update the parent task start and end dates for any and all subtask updates.  Implied is that ...

  1. Сообщество
  2. Product Feedback
  3. [Status: Coming Soon...🕑] Allow Subtasks to Update Start and End Dates of Parent Tasks

Hi. We are in the middle of a wrike rollout for our entire organization.  I've been closely watching this thread, since the parent/rollup tasks have been a sticking point for us. I hate to start ou...