Dependency
Hi,
After I added dependencies the dates of the tasks were moved.
Parece que ainda não traduzimos a página que você está buscando, mas temos conteúdo em português e disponibilizamos suporte em português.
Navegar na central de ajuda em portuguêsEnviar uma solicitação
It looks like you're trying to figure something out.
Stuck or just want advice?
You can unlock the true value of Wrike in our Community
Connect with thousands of leading teams, learn best practices, and shape the future of the product. What are you waiting for?
Now other members can find, vote, and discuss your idea.
Our Community Team reads every suggestion (yes, every one) then compiles and shares the feedback with our Product Team. Happy posting!
More about Product FeedbackComo podemos ajudar?
Learn. Share. Discuss.
Now other members can find, vote, and discuss your idea.
Our Community Team reads every suggestion (yes, every one) then compiles and shares the feedback with our Product Team. Happy posting!
More about Product FeedbackHi,
After I added dependencies the dates of the tasks were moved.
Folllowing List for Post: Dependency
[this list is visible for admins and agents only]
Hello,
If you use dependencies you want the dates to be related to the task.
However, in most project management solutions you are able to specify a lag.
In every project we have a task that will start 1 day after a predecessor.
Or we have a task that will start on the last day of the predecessor.
Would Wrike please include the option to create a lag so that we can improve management of our project timings.
Thanks
Sylvia
Thanks for your posts here guys. Can you check out Megan's post about creating leads and lags? If this meets the same requirements you're requesting please vote for her post and let me know and I'll redirect other members that visit this thread to Megan's too 👍