Multiple predecessors

Hello, 

Is it possible to make a task with multiple predecessors? How to write it? 

For example, Task C can begin while Task A and Task B are Finished? 

Thanks; 
Maxime 

0
1件のコメント
Spot On Innovative Approach Stellar Advice
Avatar
Hello Maxime, welcome to the Community 👋🏻
 
You can have multiple predecessors of a task. To do that on the Gantt Chart, double click on the Predecessors column on the table and create the dependency. Alternatively, open the task by clicking on the window icon that appears when you hover over a task. From the pop-up window, you can edit the dependencies.
 
  
Please let me know if this helps 🙋🏻‍♀️

Cansu Community Team at Wrike Wrike Product Manager Learn about Wrike’s killer features and best practices with our Online Training Webinars

Cansu Wrike Team member Learn about Wrike’s killer features and best practices with our Online Training Webinars

2
コメントアクション Permalink

Folllowing List for Post: Multiple predecessors
[this list is visible for admins and agents only]

トップ
Didn’t find what you were looking for? Write new post