When will Wrike show dependencies that are outside of the current folder in Gantt chart view? I understand that the task number is relative to the current view but I'd like some indication that th...
When adding a folder/project to a task in the task info window the search depth/scope of that feature is extremely limited. It appears to only search 2 or 3 layers deep in the project tree. If a...
If you're on labs and have been taking advantage of branch roll-up like I have then you may be enjoying this much needed feature. It does come with some limitations though. When you're using it t...
Please disable, or reduce the greying out of the background when the duplicate task dialog is in the foreground. I can't read the folder names and since the folder search doesn't work when there a...
I have a project where subtasks run several levels deep. I'm not able to effectively use the "add folder/project" search to tag my tasks because the search doesn't return the correct results. I'm...
I'd like the default view (board in this case) to always show tasks from subfolders. I can't see anyway to do that. Is that buried somewhere?
If you need to go back and adjust the due date of a task that was previously marked completed you'll need to mark that task and all its successors in progress before you shift the date. If you shi...
When searching for subtasks i.e. as a predecessor, subtasks do not show their associated folders beneath the results since they have ghost tags. This makes it incredibly difficult to setup large ...
When adding a folder/project to a task/folder the search is global within your company's Wrike account, which is great in some circumstances. In my situation where we're utilizing templates that d...
I have a schedule template that I'm working from. When I go to populate that template for the new project I add assignees, dates, general updates. The start dates for tasks without dependencies n...