How can i assure automatic date update of a successor of a task using the min/max functionality?
Hi,
the automatic date update of a successor only works if the predecessor task has fixed dates. Since my predecessor has several subtasks i use the min/max functionality. Using the min/max option the automatic date update for the successor does not work anymore.
Example without min/max - works:
-> update Task 3 end date to 22/11/2023 results in Task 4 automatically changing the start date to 23/11/2023
Example with min/max - does not work:
-> update Task 3.2 end date to 22/11/2023 results in automaticall changing Task 3 end date to 22/11/2023 because min/max is activated
-> Task 4 does not automatically change the start date to 23/11/2023
How can i make sure, that the successor dates update automatically when its predecessor is a parent task using the min/max functionality?
Thanks in advance!
Hi Lena Kron, welcome to the Community! Thank you for sharing your use case with us, I've created a Support Ticket on your behalf and one of our agents will contact you shortly to assist you with this.
Allow me to mention that you can check our New to Community forum to discover all the resources you can find in our Community 🙂
This was solved in February 2024. Thanks! :)
Glad you liked the update Lena Kron 🙂
Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover
Lisa Wrike Team member Become a Wrike expert with Wrike Discover