Activité récente par Jason Shechter
Trier par activité récente Activité récente Votes
  1. Communauté
  2. Product Feedback

Show predecessors outside the current folder

When will Wrike show dependencies that are outside of the current folder in Gantt chart view?  I understand that the task number is relative to the current view but I'd like some indication that th...

  1. Communauté
  2. Product Feedback

Please increase search depth when looking for folders to tag

When adding a folder/project to a task in the task info window the search depth/scope of that feature is extremely limited.   It appears to only search 2 or 3 layers deep in the project tree.  If a...

  1. Communauté
  2. Best Practices

Branch Roll-Up With Dependencies

If you're on labs and have been taking advantage of branch roll-up like I have then you may be enjoying this much needed feature.  It does come with some limitations though.  When you're using it t...

  1. Communauté
  2. Product Feedback

Don't grey about the background when duplicating a task

Please disable, or reduce the greying out of the background when the duplicate task dialog is in the foreground.  I can't read the folder names and since the folder search doesn't work when there a...

  1. Communauté
  2. Product Feedback

Enable greater search depth for "Add folder/project"

I have a project where subtasks run several levels deep.  I'm not able to effectively use the "add folder/project" search to tag my tasks because the search doesn't return the correct results.  I'm...

  1. Communauté
  2. How To

How do I set "Show Tasks From Subfolders" as a default view option?

I'd like the default view (board in this case) to always show tasks from subfolders.  I can't see anyway to do that.  Is that buried somewhere?

  1. Communauté
  2. Best Practices

Updating Due Dates on Completed Tasks

If you need to go back and adjust the due date of a task that was previously marked completed you'll need to mark that task and all its successors in progress before you shift the date.  If you shi...

  1. Communauté
  2. Product Feedback

Allow Ghost Tags to Show Up In Search Results

When searching for subtasks i.e. as a predecessor, subtasks do not show their associated folders beneath the results since they have ghost tags.   This makes it incredibly difficult to setup large ...

  1. Communauté
  2. Product Feedback

Option to limit "add folder/project" to current project

When adding a folder/project to a task/folder the search is global within your company's Wrike account, which is great in some circumstances.  In my situation where we're utilizing templates that d...

  1. Communauté
  2. Product Feedback

Add a "Today" Button to the date selector in Gantt chart view

I have a schedule template that I'm working from.  When I go to populate that template for the new project I add assignees, dates, general updates.  The start dates for tasks without dependencies n...