Il semble que la page que vous recherchez n'existe pas dans votre langue. Mais nous proposons d'autres contenus en français ainsi qu'une assistance en français.
It looks like you're trying to figure something out.
Stuck or just want advice?
You can unlock the true value of Wrike in our Community
Connect with thousands of leading teams, learn best practices, and shape the future of the product. What are you waiting for?
Now other members can find, vote, and discuss your idea.
Our Community Team reads every suggestion (yes, every one) then compiles and shares the feedback with our Product Team. Happy posting!
More about Product FeedbackEn quoi pouvons-nous vous aider ?
Learn. Share. Discuss.
Lag option is really a missing feature in Wrike. I have just tried to add 3 days between two tasks but when I did that, Wrike understood that as a constraint (Wrike understood that the second task ...
I agree.... this feature would save a lot of time.
Today I was analyzing a given task. The start date was 14JAN and the finish data was 18JAN. The collaborator finished the task only today (05FEB) BUT for Wrike, in every place I looked for, looks f...
This is something I'm looking for. Wrike allows to add a extra field set to percentage which works great with tasks under a project. If users type the progress of each tasks in percentage in this f...