Community

Welcome 🖖

Hi there! 🙂 Want to become a black belt Wrike Ninja? Here's how to earn a Wrike badge

Welcome 🖖 Have you checked out this week's Release Notes yet?

Hey! 👋 Curious about something? Visit How To to search and ask the Community for answers.

Welcome! 👋 Figured out a good tip or trick? Share it in Best Practices.

Want to connect your existing software to Wrike? Learn and ask how in the API section.

En quoi pouvons-nous vous aider ?

par ex. Diagramme de Gantt, Créer des tâches, Partager des dossiers...

Thick Gantt Chart Task??

2 commentaires

  • Spot On! 👍 Innovative Approach 💡 Stellar Advice 💪
    Avatar
    Ryan Slack

    I would also like to know what the thicker line represents.  I thought maybe it had to do with a task that had an updated due date, but I am not sure that is it. 

    Is this helpful? 0
    Actions pour les commentaires Permalien
  • Spot On! 👍 Innovative Approach 💡 Stellar Advice 💪
    Avatar
    Lisa

    Hey guys, thanks for bringing that up 🙂

    The thick line in front of a dependent task is a Date Constraint that signals the earliest date that a task can begin. Please check out our Help Center page on Date Constraints to learn more about it and get back here if anything's unclear 👍

    Lisa Community Team at Wrike 🌎Discover... Wrike Discover and become a Wrike expert. Click here to get started

    Is this helpful? 0
    Actions pour les commentaires Permalien

Vous devez vous connecter pour laisser un commentaire.

Folllowing List for Post: Thick Gantt Chart Task??
[this list is visible for admins and agents only]

Community

Welcome 🖖

Hi there! 🙂 Want to become a black belt Wrike Ninja? Here's how to earn a Wrike badge

Welcome 🖖 Have you checked out this week's Release Notes yet?

Hey! 👋 Curious about something? Visit How To to search and ask the Community for answers.

Welcome! 👋 Figured out a good tip or trick? Share it in Best Practices.

Want to connect your existing software to Wrike? Learn and ask how in the API section.