How can I set a default view for Tasks inside Projects?

I create a new project and add some tasks to it, then change the view to customise the visible fields.

If i now create a new project, and add some tasks to it, I have to re-do the same customisation. How do I set a default view that persists across the space?

Thanks :)

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
1 comentario

Hi Adam Mitchell,

you have 2 options:
1- Create a Blueprint, setup your customization, then every time you start from a blueprint it'll mantains the customizations.
2- Clone an existing project, so you need to create one "empty" projet with all customizations you need, and just clone project.

Hope it helps