  1. Community
  2. How To

Delayed Start Date to avoid batching work

Is there  a way to have a task start shortly after a predecessor task starts, but not necessarily waiting for the predecessor task to end completely?  The predecessor task does not need to be compl...

  1. Community
  2. How To

Task specific calendar

Is there a way to create a calendar and assign it to a specif task?  We have a supplier that has an annual shutdown and if the task of production gets pushed out to this time, I need to ensure the ...

  1. Community
  2. Product Feedback

Please make the subtask start and end dates roll up to parent tasks that use dependencies

Project plans are developed in the initiating phase of the project.  They are then progressively elaborated upon during the planning and monitoring and controlling phases.  It is unreasonable to te...

  1. Community
  2. Product Feedback

[Released] Adding the Duration Column to the timeline view

Earlier today, I submitted a request to add the Duration column into the timeline view of wrike.  This will allow a project manager to review the task, the duration, the predecessors, and assignee ...

  1. Community
  2. Product Feedback

Product Enhancement - Table view and Timeline view and critical path

Hello: I'm a project manager, trying to manage a project using Wrike.  In reviewing durations and the critical path of a project, it would be most helpful to have in the timeline view and the table...

  1. Community
  2. Product Feedback

Copying a project - need to include additional columns

Hello - I used the additional column in the timeline view to add the functional owner to the project.  When I went to copy the project, the additional column heading was copied over, however, the c...

  1. Community
  2. Product Feedback

dates from subtasks are not rolling up to the main task

  In the example, the start and end dates of the Project scope would start on the earliest date and then end on the latest subtask end date.     by making the dependent task, dependent on a subtas...

  1. Community
  2. How To

Dates set in Stone?

How do you get rid of a date if you remove a dependency?    

  1. Community
  2. How To

Start to Finish option

Is there a way to base a start and end date off of the end date of a project.  For example:  We know that 6 weeks prior to a launch we have to start working on marketing collateral.  Is there a way...

  1. Community
  2. Product Feedback

[Duplicate] adding duration into the timeline view

is there a way to be able to add duration into the New Timeline view?  I see start, end, dependency.  If the duration could be added, adding the dependency would allow the timeline to create the st...