  1. Community
  2. Wrike Analyze
  3. Formula to Calculate Business Days of the Past Month

Pietro Poli, I noticed I had to a request to have these fields enabled by support. To utilize this you have to click on the widget's ellipses, change data source, and then select "Utilization & Per...

  1. Community
  2. Wrike Analyze
  3. Formula to Calculate Business Days of the Past Month

THANK YOU! So easy and simple. I can't believe I missed it.  

  1. Community
  2. Product Feedback
  3. Milestones Do Not Properly Reschedule Based on Dependencies

For the curious, the workaround we did is similar to Juan's. I've set the "milestone" as a task but give it a duration as 1 minute and made "non-billable". Now the milestones (which are really task...

  1. Community
  2. Best Practices
  3. When adjusting dates for tasks that have predecessors, they become backlogged (losing duration, start date, end date)

Hey John Herbst, if you click the task the edit history will appear in the red box below. This has saved me several times after blowing up my scheduled. 

  1. Community
  2. Best Practices
  3. When adjusting dates for tasks that have predecessors, they become backlogged (losing duration, start date, end date)

Thank you Lisa. I did discover the, "Recalculate duration automatically" which I have enabled giving me the MS project like functionality I was looking for. I'm still genuinely curious why the date...

  1. Community
  2. How To
  3. Best way to do % complete in wrike? (in a custom field)

Hey Vivek Bhatia, I wanted to let you know that this is possible now. What you do is: 1. Create a custom field 2. Select "Percent" 3. Under "Default Aggregation" switch it to "Average" 4. Enter in ...

  1. Community
  2. Product Feedback
  3. Locking Sorting

Hi Elaine, that's a good solution. I also ended up discovering that if you sort by priority and all of the tasks are at the same priority, then the order you place them in is maintained when you re...

  1. Community
  2. Product Feedback
  3. Locking Sorting

We found the best way to deal with this was to sort by start date and a combination of a. b. c . that brought it back in order. Not ideal, but there should be a "sort by task creation order". 