HOW TO MAKE RECURRENCES OF TWO OR MORE ACTIVITIES WITH DEPENDENCES ?
Dears,
i would like to create a mountly routine of two activities in one dependent from the other with this rule: act1 1 day before act2
the best solution could be create a main task with these two subtask (act1 and act2), create dependence and duplicate tha main task with internal structure of subtask. i saw it is not possible
Is there another system ?
Hi nicola mariucci, welcome to the Community! 🙂
Because dependencies aren't preserved when you make tasks recurrent, I'd suggest this:
1) Create two tasks for act1 and act2
2) Make them both recurrent and create a certain amount of tasks upfront
3) Open them in Gantt Chart and add dependencies for them
You will then have those two monthly tasks with dependencies. Please let me know if you have any further questions, I'll be happy to discuss 👍