Subtasks Predecessors Controlling Parent Task
I believe the subtasks could be much more useful if this was possible.
Name Predecessor
1 Task 1
2 Task 2 1FS, (4FF might not be necessary depending on implantation)
3 Subtask 1 2SS <---- (can't currently do)
4 Subtask 2 3FS
5 Task 3 2FS <---- (can't currently do)
Currently you can't set predecessors on tasks that don't have dates assigned. Once dates are assigned to the parent task, the subtasks won't push out the end date of the parent task if the subtasks are scheduled past the parent task end date. Currently in this case the parent task is shown extended with a transparent extension but that extension has no effect on anything (i.e. can't be used as a predecessor).
It would be a simple matter to allow setting predecessors from other tasks directly to a parent task with subtasks. This would allow creating a task with predecessors set to other tasks as usual. Then at a later date add subtasks under a parent task and set the predecessors of the subtasks to the parent task to allow the subtasks to control the start and end date of that parent task. Adding subtasks to any parent task would NOT require you to modify the dependencies already set up between parent tasks.
Currently you have to connect the subtask from under one parent task to a subtask under the next parent task to create the correct dependencies. This makes no sense if you support hierarchical task structures.
This would enable parent tasks with their associated subtasks to be treated as a package with other tasks linking to and from only the parent task with the subtasks controlling the duration of each parent task they are under.
This seem like a basic function that for some reason is missing and would address several problems mentioned in product feedback.
I think we are experiencing the same issue, if I'm understanding Ray correctly. By the nature of being a SUBTASK, the relationship is assumed to the parent.
The missing relationship is causing similar issues for us. The subtask becomes an outlier when we start adjusting durations on parent tasks and it does not move along with those tasks.
Same issue for me. If we assume the subtasks are components of the parent task, then the parent task should not have a pre-specified duration. That should depend on the durations of the subtasks and how they are linked.
Thanks for your suggestion and support here! I really think this is a very interesting idea. I'll try to mention this thread where possible on the Community 🙂 To get a status from the Product team, the post will need 60 upvotes from the members.
Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover
Lisa Wrike Team member Become a Wrike expert with Wrike Discover
Hi everyone who reads this, hope you're well!
I'm adding this comment in the hopes that someone found a solution or workaround, or in the hope that someone else in my situation feels some sanity knowing that this issue still persists.
Kevin Isernio How about a finish-finish dependency on the parent task? Could that help? It will shift the parent task end. Unfortunately also shifting the start of the parent task. You could link the first subtask to a predecessor so you will keep your project plan.
Hi Sven Passinger
Thank you for following up-- following your example above, why would the start for "test parent" be affected by "test subtask"? If the dependency is based upon the finishing of things, i.e. "FF". Is there any way for this not to happen?
Surely if I started a task 2 months ago, and now create a new subtask within it which adds two days, I would only desire the expected end date to adjust rather than the initial start date. It seems as though as a default, Tasks should not be able to start until a project does, and a subtask should not be able to start before a task does. So a task's duration is comprised of the aggregate duration of the subtasks within it and determined by how those subtasks are dependent upon each other. Similarly, a project's duration is comprised of the aggregate duration of the tasks within it and how determined by how those tasks are depended upon each other. Things start ASAP by default, whereas a task cannot start until a project has begun, and a subtask cannot begin until its parent task has begun. This way I can enter in a start date for a project, and it would spit out a projected finish date. Then as things come up, as I decide to add subtasks within a task, or extend or shorten the duration of a subtask, the ultimate projected end date for the project would properly update. Let me know if this helps.
Kevin Isernio I do not know any way that ff correlation does not shift the starting date. Lisa is their any way to make Wrike shift the task end date but let the start day remain the same (so to change the duration of the task)?
Hi Kevin Isernio, Sven Passinger, at the moment, the dates will shift in this situation, you can find out more in this Help Center article.
I do however understand the use case here, and I've shared your feedback with the Product team👍🏼
Late to the party, but was this ever address? Or a work around found? I have Tasks that I would like to break down into subtask that would actually affect the parent. Thanks,
Hi Gimo Barrera, welcome to the Community 👋
I've asked our Support engineers to look into your question, and I can see they've contacted you 👍 Let me know if you need help with anything else. And here's the forum for new Community members to get you started.
Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover
Lisa Wrike Team member Become a Wrike expert with Wrike Discover
Lisa - Can I get the information on subtasks as well?
Hi Lori Perrault, I've asked the team to follow up with you also. Let me know if you need anything else.
Elaine Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover
Elaine Wrike Team member Become a Wrike expert with Wrike Discover
Hi Team,
Is there a status on this request? It would be extremely helpful to have this functionality for project planning!
Thanks,
Ashley
Hey Ashley Sabol, thank you for checking in here and welcome to Community 🙂
No update to share here unfortunately. This votes for this request are on the lower side, which means there's less of a priority attached to this request. Read more about how we work with Product feedback in this Community post. If you do need further assistance, or if there's anything else we can help with, please don't hesitate to ask.
Elaine Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover
Elaine Wrike Team member Become a Wrike expert with Wrike Discover
I'll drop a vote for this. I have a parent task for a series of interviews. Below it, I have multiple sub-tasks for each interview. The next step can begin when ALL interviews are complete. Currently, the predecessor on the next step will have to list all individual interviews (i.e. all sub-tasks) instead of the single parent task.
Hello Eric Gilbertsen, welcome to the Community! Thank you for adding your vote and for sharing your use case with us, I've passed it over to our relevant team and we will keep you updated if there are any changes.
Please, feel free to visit our New to Community forum to get the most out of your experience with our Community 🙂
If you have any additional questions, please let us know.