How to view tasks that were completed past their original due date?

5 comments

  • Spot On! ๐Ÿ‘ Innovative Approach ๐Ÿ’ก Stellar Advice ๐Ÿ’ช
    Avatar
    Lisa

    Hey Thomas, thanks for reaching out ๐Ÿ‘‹

    There's a "Completed date" filter option that can help track when the tasks were completed, no matter what the due date is.

     

    For example, I have a task that was due on April,2 but I completed it today on July,8 - that task is shown as "Completed today":

    This is pretty manual but allows you to track the completion dates. I hope this helps and let me know if you'd like to discuss this further ๐Ÿ™‚

    Lisa Community Team at Wrike ๐ŸŒŽDiscover... Wrike Discover and become a Wrike expert. Click here to get started

    Is this helpful? 0
    Comment actions Permalink
  • Spot On! ๐Ÿ‘ Innovative Approach ๐Ÿ’ก Stellar Advice ๐Ÿ’ช
    Avatar
    Steven Getes

    Sorry for re-opening this thread because I am also interested with this to check my team's performance in completing tasks within the agreed deadline. 

    If I understood it correctly in this thread, there is currently no way for you (aside from doing manually) to check the days delayed in completing a task. 

    Is this helpful? 0
    Comment actions Permalink
  • Spot On! ๐Ÿ‘ Innovative Approach ๐Ÿ’ก Stellar Advice ๐Ÿ’ช
    Avatar
    Lisa

    Hey Steven Getes, welcome to the forums! ๐Ÿ™‚

    It's also possible to create a report based on any tasks you need and to monitor due and completed dates with it:

    Please feel free to ask any questions, I'm here to help ๐Ÿ™‚

    Lisa Community Team at Wrike ๐ŸŒŽDiscover... Wrike Discover and become a Wrike expert. Click here to get started

    Is this helpful? 0
    Comment actions Permalink
  • Spot On! ๐Ÿ‘ Innovative Approach ๐Ÿ’ก Stellar Advice ๐Ÿ’ช
    Avatar
    Steven Getes

    Hey Lisa,

     

    So I kind of figured it out earlier but it has to be done manually. 

    I added a custom field to input the actual completion date and then added another custom field to subtract actual completion to the due date. 

    I imagine that in the screenshot you showed here above that completed date is also added manually? I was hoping that this was something that can be done automatically. 

     

    Steve

    Is this helpful? 0
    Comment actions Permalink
  • Spot On! ๐Ÿ‘ Innovative Approach ๐Ÿ’ก Stellar Advice ๐Ÿ’ช
    Avatar
    Lisa

    Thanks for getting back to me, Steven Getes

    To be able to see the completed date in the report, you just click on the gear icon in the upper left corner and check the "Completed date" column Those settings are saved once you save the report ๐Ÿ‘

    Lisa Community Team at Wrike ๐ŸŒŽDiscover... Wrike Discover and become a Wrike expert. Click here to get started

    Is this helpful? 0
    Comment actions Permalink

Please sign in to leave a comment.

Folllowing List for Post: How to view tasks that were completed past their original due date?
[this list is visible for admins and agents only]

Community

Welcome ๐Ÿ––

Hi there! ๐Ÿ™‚ Want to become a black belt Wrike Ninja? Here's how to earn a Wrike badge

Welcome ๐Ÿ–– Have you checked out this week's Release Notes yet?

Hey! ๐Ÿ‘‹ Curious about something? Visit How To to search and ask the Community for answers.

Welcome! ๐Ÿ‘‹ Figured out a good tip or trick? Share it in Best Practices.

Want to connect your existing software to Wrike? Learn and ask how in the API section.