Board View - Advanced Filter - Task Type

In "Board View" there is an advanced filter called "Task Type" that I am interested in.  It has three options "Planned" "Milestone" and "Backlogged" 

I looked for explanations on https://help.wrike.com/hc/en-us/articles/115000193205-Board-View#sorting  but didn't find any.  

Is this an accurate description?

Planned = Tasks scheduled for today or a future date.

Milestone = Task set to the Milestone status

Backlogged = Task schedule in the past.

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
1 comment

Hey Ryan, thanks for posting!

A planned task is a task with scheduled start and due dates.

A Milestone task is scheduled for one day and has no duration. Milestones are used as reference points to mark a major event or a branching decision point in a project.

A Backlogged task does not have scheduled start and end dates.

Hope it helps 🙂

Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Lisa Wrike Team member Become a Wrike expert with Wrike Discover

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Board View - Advanced Filter - Task Type
[this list is visible for admins and agents only]

Top
Didn’t find what you were looking for? Write new post