Include a different due dates on same task.

2 comments

  • Spot On! 👍 Innovative Approach 💡 Stellar Advice 💪
    Avatar
    Saad Fahim

    Must have

    Is this helpful? 4
    Comment actions Permalink
  • Spot On! 👍 Innovative Approach 💡 Stellar Advice 💪
    Avatar
    Ami Novak

    We are currently using subtasks to do that.  It makes reporting stickier, but it has worked from a deadline standpoint.  The challenge we've faced is that missed deadlines don't automatically shift dependent schedules.  That is, if first draft doesn't happen by its deadline, then the amend date doesn't shift backwards.  It stays as placed, so people are looking for items that aren't ready yet.  THAT has been problematic for our team.

    Is this helpful? 1
    Comment actions Permalink

Please sign in to leave a comment.

Folllowing List for Post: Include a different due dates on same task.
[this list is visible for admins and agents only]

Community

Welcome 🖖

Hi there! 🙂 Want to become a black belt Wrike Ninja? Here's how to earn a Wrike badge

Welcome 🖖 Have you checked out this week's Release Notes yet?

Hey! 👋 Curious about something? Visit How To to search and ask the Community for answers.

Welcome! 👋 Figured out a good tip or trick? Share it in Best Practices.

Want to connect your existing software to Wrike? Learn and ask how in the API section.