What happens if you change the status of a task that is tagged under multiple projects?

Answered

1 comment

  • Spot On! ๐Ÿ‘ Innovative Approach ๐Ÿ’ก Stellar Advice ๐Ÿ’ช
    Avatar
    Ryan Nelson

    Hi Lauren,

    If a single task is tagged into two different projects then the task will show the updated status in both projects. The projects folders will keep the assigned workflow that was last selected for the project, but the task will have the status from whatever work flow is assigned to that task.

    Hope that helps.

    -Ryan

    Is this helpful? 1

Please sign in to leave a comment.

Folllowing List for Post: What happens if you change the status of a task that is tagged under multiple projects?
[this list is visible for admins and agents only]

Community

Welcome ๐Ÿ––

Hi there! ๐Ÿ™‚ Want to become a black belt Wrike Ninja? Here's how to earn a Wrike badge

Welcome ๐Ÿ–– Have you checked out this week's Release Notes yet?

Hey! ๐Ÿ‘‹ Curious about something? Visit How To to search and ask the Community for answers.

Welcome! ๐Ÿ‘‹ Figured out a good tip or trick? Share it in Best Practices.

Want to connect your existing software to Wrike? Learn and ask how in the API section.