Can you manually sort tasks in a folder or project without a date or time?

I have a quality control checklist that I perform every morning; sometimes it's at 9am, sometimes it's at 10am.  I would like to sort the tasks in the order that I perform them, but I only see how to sort them by Dates, Importance, Priority, Status and Title.  I could just add numbers to the beginning of the titles, but that will get frustrating when I have to change them.

So, is there anyway to sort them manually?

Thanks!

0
2 comments
Spot On Innovative Approach Stellar Advice
Avatar

"Priority" in Wrike is essentially a manual sort. In list view, set the ordering to "By Priority" and drag the tasks up and down until they are in the order you perform them. In reality, this is the priority: the task you do first is highest priority, and so on.

An alternative approach would be to have a single repeating task, which is your morning QC checklist, that has all the items in the list as checkbox items in the task description (in the correct order). The task is complete when all the items are checked...

0
Comment actions Permalink
Spot On Innovative Approach Stellar Advice
Avatar
Welcome to the Community Chris Dukes 👋🏻
 
Thank you for your question and thanks Michael Cornelius for the great advice.
 
Please let me know if you still need some help 🙋🏻‍♀️

Cansu Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Cansu Wrike Team member Become a Wrike expert with Wrike Discover

0
Comment actions Permalink

Folllowing List for Post: Can you manually sort tasks in a folder or project without a date or time?
[this list is visible for admins and agents only]

Top
Didn’t find what you were looking for? Write new post