Issues with creating and rescheduling a project from a Blueprint that contains milestone tasks

Hello, 

I have set up Blueprints that contain tasks, dependencies and resources. We then create project plans from the Blueprints, check the "Reschedule" box and set the new start date. 

If the Blueprint contains no milestone tasks, then the project reschedules correctly to the new start date

If the Blueprint contains milestone tasks, it does not reschedule correctly and gives unexpected and wrong results

Because of this issue, I am currently setting up Blueprints without milestone tasks, but would like to do so going forward. What should be the correct behavior of a Blueprint that contains milestone tasks? Should they reschedule properly?

2
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
7 comments

Hi Andy Sigrist, I believe our Support team is helping with this. 

If you need anything else, don't hesitate to ask 👍

Elaine Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Elaine Wrike Team member Become a Wrike expert with Wrike Discover

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hello I also had a similar issue last week (and didn't previously used to have it). For me all the tasks rescheduled correctly, except those attached to a milestone where the milestone didn't move. Can anyone let me know if there is a solution for this? or if this is a known issue?

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
Avatar
Cansu

Hello David Benjamin, I see that our Support team is in contact with you via email. 

Please let me know if I can help with anything else 🙋🏻‍♀️

Cansu Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Cansu Wrike Team member Become a Wrike expert with Wrike Discover

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

I am experiencing similar issues. Has an easy fix been identified for this?

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hi Isabelle Couture, I'm sorry to hear you're experiencing this! I've asked my colleagues from the Support team to contact you about this to troubleshoot. I can see they've already reached out to you via email 👍

Please let me know if I can help you with anything else! 

Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Lisa Wrike Team member Become a Wrike expert with Wrike Discover

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

I have the same issue with the milestones. Any guidance?

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hi Lea Labastida, thank you for bringing this to us! I have opened a ticket with our Support team so they can assist you with this 👍

Juan M. M. Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Juan M. M. Wrike Team member Become a Wrike expert with Wrike Discover

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos