Issues with creating and rescheduling a project from a Blueprint that contains milestone tasks

Hello, 

I have set up Blueprints that contain tasks, dependencies and resources. We then create project plans from the Blueprints, check the "Reschedule" box and set the new start date. 

If the Blueprint contains no milestone tasks, then the project reschedules correctly to the new start date

If the Blueprint contains milestone tasks, it does not reschedule correctly and gives unexpected and wrong results

Because of this issue, I am currently setting up Blueprints without milestone tasks, but would like to do so going forward. What should be the correct behavior of a Blueprint that contains milestone tasks? Should they reschedule properly?

0
1 comment
Spot On Innovative Approach Stellar Advice
Avatar

Hi Andy Sigrist, I believe our Support team is helping with this. 

If you need anything else, don't hesitate to ask 👍

Elaine Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Elaine Wrike Team member Become a Wrike expert with Wrike Discover

0
Comment actions Permalink

Folllowing List for Post: Issues with creating and rescheduling a project from a Blueprint that contains milestone tasks
[this list is visible for admins and agents only]

Top
Didn’t find what you were looking for? Write new post